Composite Pipe Repair
Industry: Water & Wastewater
Solution: Raw Sewage Piping
ID: CPR-7-00129
Project summary:
The inspectors at a wastewater treatment plant discovered a leak on the elevated tee section of its intake piping. Advanced FRP System provided a 4-layer carbon fiber wrap system to repair the pipe section. The repair not only provides a structurally independent pipe around the existing pipe to prevent leaks from internal corrosion, but adds minimal weight to the structure, and prevents external corrosion.
- Date of installation: 06/21
- Facility/Location: New York
- Applicator: RPT New York
- Products used:
- FRP 200 Saturant
- CF-500 BD